流程

         
         
Description     Check Point Document or Meeting
Owner Judgement
   
1.Release RFP(PRD/HDR) Customer     1. RFP Relation document (PRD/HDR/ID…)
  & RFQ       2.Product Concept Introduction Meeting
2. Create New Project Sales      
         
         
3.RFP Study RD&RDPM   Refer RFP flow RFP's feedback
Pega RD start to research       Key parts list & Schedule
        Proposal
         
         
4.Release Proposal to Customer RD&RDPM     Proposal
        Schedule (if information is enough)
         
5. Customer review proposal  Customer   回覆Comment Proposal review meeting
and provide approval     規格Fix  
         
6. Sales provide Quote estimate Customer      
 requirement after Customer  Sales      
 provided approval        
         
7.Cost estimate PM   Refer RFQ flow BOM Cost
  RD     MVA
  PUR     Certification list
         
8.Quote Sales   Refer RFQ flow BOM Cost & NRE
        MVA
9 Start to run new project Customer      
         
         
         
         
10.new project kick off meeting Sales     1. Master schedule(Inculde SW, Key parts, certification)
        2. Organization introduction
        3. Customer parts SPEC
        4. 設計構想(Proposal/規格/爆炸圖/Key part list/FMEA)
11.Pega RD start to research updated PL     Updated proposal
         
12. Pega RD hold a Design Concept meeting  PL&PM PL   1. 設計構想(Proposal/規格/爆炸圖/Key part list/FMEA)
2. Test plan
         
13. Pega make a Design Concept presentation to Customer PL&PM Customer   1. 設計構想(Proposal/規格/爆炸圖/Key part list/FMEA)/調整要項書(test plan)
2. Test plan
3. Updated Master schedule
4. Updated Quote
         
14. Pega hold a new project introduction meeting PL&PM     1. 設計構想(Proposal/規格/爆炸圖/Key part list/FMEA)/調整要項書Test plan
2. Master Schedule
         
15.Factory feedback meeting FPM&RD     1.工廠提供建議以及組裝經驗.
2.工廠提供生
產履歷/DFM/FMEA
         
16. Start to Design for EVT PL&PM      
         
17-1. 召開EVT試作準備會議
17-2. It must be 2 weeks ago before EVT ON
PL&PM     QA重點評價項目、調整要項書,製造規格書
         
18. Prepare reference data for EVT sample run PL&PM     QA重點評價項目、調整要項書,製造規格書
         
19. 召開EVT試作ON meeting FPM&RD   齊料確認 5M check
         
20. Start EVT sample run        
         
21. 召開EVT試作close meeting FPM     試作問題點
         
22. Start 設計驗證、輻射測定、QA實驗 PL&PM     Daily test report
         
23. Pega RD hold a EVT Design Review meeting PL&PM PL & QA leader   設計驗證 test List
、QA Report
         
24. Pega and customer hold a EVT Design Review meeting PL&PM Customer   設計驗證 test List
、QA Report
         
25. Judgement meeting for transferring to DVT PL&PM PL   移行報告(設計構想檢證結果、設計驗證結果、QA report、open issue、schedule、設變項目,試做問題點)
         
26. Design change for DVT     21-1. ME tooling start, vendor selection, tooling number planning Updated Quote
27. Hold a DVT introduction meeting PL&PM     CombineList/Allocation、差異部品表、試作ECN確認List、DVT BOM、新規Data発行(SB、図面、Gerber,Mount図、回路図)
         
28-1. 召開DVT試作準備會議
28-2. It must be 2 weeks ago before DVT ON
PL&PM     QA重點評價項目、調整要項書,製造規格書,組裝貼附一覽表(格式如下)
         
29. Prepare reference data for DVT sample run PL&PM     QA重點評價項目、調整要項書,製造規格書
         
30. 召開DVT試作ON meeting FPM   齊料確認 5M check
         
31. Start DVT sample run        
         
32. 召開DVT試作close meeting FPM     試作問題點
         
32. Start 設計驗證、輻射測定、安規認證、QA實驗 PL&PM   reference safety flow Daily test report
         
         
         
34. Pega RD hold a DVT Design Review meeting PL&PM PL & QA leader   設計驗證 test List
、QA Report
         
35. Pega and customer hold a DVT Design Review meeting PL&PM Customer   設計驗證 test List
、QA Report
         
36. Judgement meeting for transferring to PVT PL&PM PL   移行報告(設計構想檢證結果、設計驗證結果、QA report、open issue、schedule、設變項目,試做問題點)
         
37. Design change for PVT PL&PM     Updated Quote
         
38. PVT&MP BOM fix PL   部品表Fix  
         
  PUR   Add "schedule II" table  
         
40. Hold a PVT introduction meeting PL&PM     Combine List/Allocation、差異部品表、DVT~PVT ECN確認、PVT BOM発行、新規Data発行(SB,圖面、Gerber,Mount圖、回路圖)
       
41-1. 召開PVT試作準備會議
41-2. It must be 2 weeks ago before PVT ON
PL&PM     PVT QA重點評價/OQC測試項目
         
42. Prepare reference data for PVT sample run PL&PM&RD     QA重點評價, PVT Check list, 5M check, SW build imager tracker 
         
43. 召開PVT試作ON meeting FPM      
         
44 Start PVT pilot run        
         
45. 召開PVT試作close meeting FPM     試作問題點
         
46. Start 設計驗證、輻射測定、安規追加申請、QA實驗 PL&PM   reference safety flow Daily test report
         
47. Pega RD hold a PVT Design Review meeting PL&PM PL & QA leader   QA品質速報、安規認証結果確認、設計検証結果、輻射測定判定依頼書、温上試験報告書
         
48. Pega and Customer hold a PVT Design Review meeting PL&PM Customer   QA品質速報、安規認証結果確認、設計検証結果、輻射測定判定依頼書、温上試験報告書
         
49. Prepare reference data for Online        
         
50. Hold a Online Judgement meeting QA QA leader   Production Specification Document
轉移文件
         
51. 針對量產產出機台, 測定Safety, EMI, QA/ADI  QA QA leader 根據客要求增加  
         
52. prepare reference data for 出貨判定 QA     出貨判定CheckList
         
53. 出貨判定 meeting QA     出貨判定CheckList
         
54. MP        
         
         
55. Saitama ODM 衍生機種       Control table release
     MP判定流程 RDPM&FPM RDPM    
         
         
56.收到FPM表單後與RD確認 RD PM&QA     Saitama延伸機種判定
   後完成後回傳廠OEM       認證/SW/HW/包材等確認是否可MP
,召開On-line判定        
57. MP delay 訊息告知客 Sales      
58. OEM與各廠單位簽核完成 OEM     Saitama延伸機種判定
    後提給生管進行MP        
         
         