Total replenishement lead time (MRP3 --> availability check)
MRP3-- > Availability check ---> Total replenishment lead time (in workdays)
For in-house produced material and it is taken into consideration in the availability check . In an availability check where the system takes the replenishment lead time into consideration, it only checks whether there are sufficient incoming quantities and stocks available to cover the requirements within the replenishment lead time. Outside the replenishment lead time,the system assumes that the material is available in sufficient quantity.
if for the material which is procured by external procurement , procurement type: F
requested PO delivery date + GR Processing time(MPR2-->scheduling) == > PO requirement/receipt date (MD04)
PO document date + planned delivery time (MPR2-->scheduling) == > realistic delivery date
Total replenishment lead time (in workdays)
The total replenishment lead time is the time needed before the product is completely available again, that is, after all BOM levels have been procured or produced. It is not calculated by the system, but defined in this field as the total of the in-house production time(s) and/or the planned delivery time(s) of the longest production path.
This time is necessary if, for materials produced in-house, the replenishment lead time is to be taken into consideration in the availability check.
In an availability check where the system takes the replenishment lead time into consideration, it only checks whether there are sufficient incoming quantities and stocks available to cover the requirements within the replenishment lead time. Outside the replenishment lead time,the system assumes that the material is available in sufficient quantity.
Therefore, in this situation, it is usually necessary to depict the product's total replenishment lead time with all BOM levels as the replenishment lead time.
Use
The following options exist for materials produced in-house if the replenishment lead time is included in the availability check:
- The Total replenishment lead time field is maintained.
- In this case, the time maintained in this field is used for the availability check.
- The Total replenishment lead time field is not maintained.
- In this case, the system reads the in-house production time and, if available, the goods receipt processing time, and interprets the total of these two times as the replenishment lead time for the availability check.
Note
There is no point in maintaining the Total replenishment lead time field for materials procured externally. In external procurement, the system adds the processing time from purchasing, the planned delivery time, and the goods receipt processing time and uses this total as the replenishment lead time for an availability check with replenishment lead time.
【推荐】国内首个AI IDE,深度理解中文开发场景,立即下载体验Trae
【推荐】编程新体验,更懂你的AI,立即体验豆包MarsCode编程助手
【推荐】抖音旗下AI助手豆包,你的智能百科全书,全免费不限次数
【推荐】轻量又高性能的 SSH 工具 IShell:AI 加持,快人一步
· Linux系列:如何用heaptrack跟踪.NET程序的非托管内存泄露
· 开发者必知的日志记录最佳实践
· SQL Server 2025 AI相关能力初探
· Linux系列:如何用 C#调用 C方法造成内存泄露
· AI与.NET技术实操系列(二):开始使用ML.NET
· 被坑几百块钱后,我竟然真的恢复了删除的微信聊天记录!
· 【自荐】一款简洁、开源的在线白板工具 Drawnix
· 没有Manus邀请码?试试免邀请码的MGX或者开源的OpenManus吧
· 园子的第一款AI主题卫衣上架——"HELLO! HOW CAN I ASSIST YOU TODAY
· 无需6万激活码!GitHub神秘组织3小时极速复刻Manus,手把手教你使用OpenManus搭建本