SAP MRP strategy group 策略组探讨

How Strategy 40 - Planning with Final Assembly Works

40: MTS ; normally , it is for standard parts .

Strategy 40 :-

1. Stocks on hand reduces the PIR during MRP run. 
e.g. if stock is 100 and PIR is 100, MRP run will not prompt 100 for procurement. if stock is 0 and PIR is 100, MRP run will prompt 100 for procurement.

2. Sales order creation reduces the PIR.
e.g. if PIR is 100, sales order 90, PIR becomes 10(withdrawal 90).

3. Delivery reduces the Sales Order.

Planned independent requirements are consumed by incoming sales orders so that the master plan is always adjusted to suit the current requirements situation. 
You must maintain the following master data for the finished product in the material master:

Strategy group 40 on the MRP screen. 
- Consumption parameters (Consumption mode, Bwd consumption, Fwd consumption) to allow consumption of independent requirements. If no consumption parameters are maintained in the material master, the system uses default values are taken from the MRP group. 
- To control consumption, you maintain a consumption mode as well as a consumption period. 

Item category group (for example, NORM) on the Sales Organization Data screen.

Four important points :-

1. Planned independent requirements are used to trigger the procurement and production of the necessary assemblies and components before receipt of the sales orders. 

2. As soon as the sales order is received, it consumes the planned independent requirements. 

3. An ATP (available to promise) logic during sales order processing will checks whether sufficient planned independent requirements have been planned to cover the sales order. 

4. Requirements from the sales orders are passed on to production and can lead to changes made to procurement if the requirements from the sales orders exceed the planned ndependent requirement quantities. If there is insufficient coverage of components (the sales order quantities exceed the planned independent requirement quantities), the sales orders cannot be confirmed. The system therefore automatically adjusts the master plan. Planned independent requirement quantities that are left unconsumed increase the warehouse stock of the finished product.

posted @   jefflu99  阅读(3064)  评论(0编辑  收藏  举报
编辑推荐:
· Linux系列:如何用heaptrack跟踪.NET程序的非托管内存泄露
· 开发者必知的日志记录最佳实践
· SQL Server 2025 AI相关能力初探
· Linux系列:如何用 C#调用 C方法造成内存泄露
· AI与.NET技术实操系列(二):开始使用ML.NET
阅读排行:
· 被坑几百块钱后,我竟然真的恢复了删除的微信聊天记录!
· 【自荐】一款简洁、开源的在线白板工具 Drawnix
· 没有Manus邀请码?试试免邀请码的MGX或者开源的OpenManus吧
· 园子的第一款AI主题卫衣上架——"HELLO! HOW CAN I ASSIST YOU TODAY
· 无需6万激活码!GitHub神秘组织3小时极速复刻Manus,手把手教你使用OpenManus搭建本
点击右上角即可分享
微信分享提示