Automatic Source Determination in the Procurement Process

You can automate various steps in the procurement process. Thus, material requirements can be determined through materials planning. This relieves the burden on user departments, since it is not necessary for purchase requisitions for required items to be created manually. The automatic conversion of requisitions into purchase orders is another way of simplifying the procurement process.

Figure 157: Automated Procurement: Source Determination

To be able to convert an item of a purchase requisition into a PO automatically, the system must know from which vendor and at which price the material is to be procured.

When creating the purchase requisition, the requester can choose a source for the item. As a rule, however, the purchasing department is responsible for assigning sources. In the source selection process, you can have the system support you by suggesting a list of existing sources.

Figure 158: Conversion of Requisition into a Purchase Order

A source of supply can be both a vendor (external supplier) and one of your enterprise's own plants. External sources are represented by purchasing info
records and outline agreements. For these sources or supply, the vendor and the price of the material can be taken from the relevant record or document.

Figure 159: Overview of Sources of Supply

A purchasing info record is a repository of information for purchasing. It contains data on a certain material and the supplier of that material. The information may
include the current vendor price, the vendor's planned delivery time, and the name by which the vendor refers to the material.
An outline agreement is a longer-term arrangement with a vendor for the supply of materials or provision of services based on predefined terms and conditions.
This arrangement is valid for a certain period and for a predetermined total purchase quantity or value. There are two types of outline purchase agreement:
• Contract
• Scheduling agreement

An outline agreement does not contain specific delivery dates or quantities of individual deliveries. You specify these subsequently, in either a contract release
order or a scheduling agreement delivery schedule, depending on the type of agreement. In the next section, we take a closer look at the contract.

 

posted @   jefflu99  阅读(304)  评论(0编辑  收藏  举报
编辑推荐:
· Linux系列:如何用heaptrack跟踪.NET程序的非托管内存泄露
· 开发者必知的日志记录最佳实践
· SQL Server 2025 AI相关能力初探
· Linux系列:如何用 C#调用 C方法造成内存泄露
· AI与.NET技术实操系列(二):开始使用ML.NET
阅读排行:
· 被坑几百块钱后,我竟然真的恢复了删除的微信聊天记录!
· 【自荐】一款简洁、开源的在线白板工具 Drawnix
· 没有Manus邀请码?试试免邀请码的MGX或者开源的OpenManus吧
· 园子的第一款AI主题卫衣上架——"HELLO! HOW CAN I ASSIST YOU TODAY
· 无需6万激活码!GitHub神秘组织3小时极速复刻Manus,手把手教你使用OpenManus搭建本
点击右上角即可分享
微信分享提示