Material Requirement Planning in SAP Vs SAP SCM:

Material Requirement Planning in SAP Vs SAP SCM:

Key words: SCM-APO , ECC-MRP , APO-finite capacity and constraints

 

The SAP R/3 or ECC has a MRP system that plans for material and capacity (schedules) without considering any constraint and by assuming availability of infinite capacity for the work centers. This gap of SAP ECC was later-on removed with the help of an add-on or a plug-in introduced  by SAP for the advanced planning of requirements; it was called SCM - APO (Supply Chain Management - Advanced Planning Optimizer). This tool worked on much complex and much supreme heuristics with the capability of planning based on finite capacity and constraints. The SCM - APO had modules such as Demand planning which was a superlative version of Sales and Operation Planning (SAP - SOP) in SAP ECC, Supply Network Planning which allowed planning across plants and across geographical locations and allowing businesses to place orders for production or procurement across the global based on time and cost contraints and the PPDS module (Production planning and detail scheduling) which was a detailed version of SAP ECC plant level MRP based Production planning with more brainy heuristics codes which could consider multiple contraints and finite based planning situations in one planning run. 

posted @   jefflu99  阅读(451)  评论(0编辑  收藏  举报
编辑推荐:
· Linux系列:如何用heaptrack跟踪.NET程序的非托管内存泄露
· 开发者必知的日志记录最佳实践
· SQL Server 2025 AI相关能力初探
· Linux系列:如何用 C#调用 C方法造成内存泄露
· AI与.NET技术实操系列(二):开始使用ML.NET
阅读排行:
· 被坑几百块钱后,我竟然真的恢复了删除的微信聊天记录!
· 【自荐】一款简洁、开源的在线白板工具 Drawnix
· 没有Manus邀请码?试试免邀请码的MGX或者开源的OpenManus吧
· 园子的第一款AI主题卫衣上架——"HELLO! HOW CAN I ASSIST YOU TODAY
· 无需6万激活码!GitHub神秘组织3小时极速复刻Manus,手把手教你使用OpenManus搭建本
点击右上角即可分享
微信分享提示