Difference between MRP vs MPS
Explain the difference between MRP & MPS. Though both components gives you the requirement list, what we gain out of MPS run rather than running MRP. What is the main idea behind this?
The following might help in explaining the difference between MPS and its counter part MRP.
Master Production Schedule (MPS) :
MPS operates within only one level of the BOM, While MRP can be utilized
throughout all levels of a material’s BOM. If a MPS is
run on a material, the necessary orders are planned at that level. Dependent
requirements (if any) are placed on the next BOM level down, and then the
process stops.
Main Idea : Master production scheduling (MPS) is a form of MRP that concentrates planning on the parts or products that have the great influence on company profits or which dominate the entire production process by taking critical resources. These items are marked as ‘A’ parts (MPS items) and are planned with extra attention. These items are selected for a separate MPS run that takes place before the MRP run. The MPS run is conducted without a BOM explosion so that the MRP controller can ensure that the Master schedule items (MSI) are correctly planned before the detailed MRP run takes place.
The master production schedule is a line on the master schedule grid that reflects the anticipated build schedule for those items assigned to the master scheduler. The master scheduler maintains this schedule, and in turn, it becomes a set of planning numbers that drives material requirements planning. It represents what the company plans to produce expressed in specific configurations, quantities, and dates. The master production schedule is not a sales item forecast that represents a statement of demand. The master production schedule must take into account the forecast, the production plan, and other important considerations such as backlog, availability of material, availability of capacity, and management policies and goals. Syn: master schedule.
Material Requirements Planning (MRP) :
A set of techniques that uses bill of material data, inventory data,
and the master production schedule to calculate requirements for materials.
It makes recommendations to release replenishment orders for material.
Further, because it is time-phased, it makes recommendations to reschedule
open orders when due dates and need dates are not in phase. Time-phased
MRP begins with the items listed on the MPS and determines
(1) the quantity of all components and materials required to fabricate those items and
(2) the date that the components and material are required. Time-phased MRP is accomplished by exploding the bill of material, adjusting for inventory quantities on hand or on order, and offsetting the net requirements by the appropriate lead times.
MRP Interview Questions:
What is the need of mrp list if stock requirement list is already there?
The MRP list displays the result of the last planning run. Changes that have occurred between planning runs are ignored in the MRP list. In contrast to this, the system displays all changes in stock, receipts and issues, which have currently occurred, in the stock/requirements list.
Which tcode are used to run MRP?
- MD01 is generally used to run the MRP for all the materials in a plant
normally just before go-live.
- MD02 is used to run MRP for materials which have a BOM i.e multi-level.
- MD03 is used to run MRP for materials which do not have a BOM i.e
single level.
【推荐】国内首个AI IDE,深度理解中文开发场景,立即下载体验Trae
【推荐】编程新体验,更懂你的AI,立即体验豆包MarsCode编程助手
【推荐】抖音旗下AI助手豆包,你的智能百科全书,全免费不限次数
【推荐】轻量又高性能的 SSH 工具 IShell:AI 加持,快人一步
· Linux系列:如何用heaptrack跟踪.NET程序的非托管内存泄露
· 开发者必知的日志记录最佳实践
· SQL Server 2025 AI相关能力初探
· Linux系列:如何用 C#调用 C方法造成内存泄露
· AI与.NET技术实操系列(二):开始使用ML.NET
· 被坑几百块钱后,我竟然真的恢复了删除的微信聊天记录!
· 【自荐】一款简洁、开源的在线白板工具 Drawnix
· 没有Manus邀请码?试试免邀请码的MGX或者开源的OpenManus吧
· 园子的第一款AI主题卫衣上架——"HELLO! HOW CAN I ASSIST YOU TODAY
· 无需6万激活码!GitHub神秘组织3小时极速复刻Manus,手把手教你使用OpenManus搭建本