项目进度及项目组近期任务说明
1,项目进度
|
ERP项目实施细节 |
2005年 |
2006年 |
|||||||||||||||
|
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
11 |
12 |
1 |
2 |
3 |
4 |
5 |
6 |
||
01 |
² 项目启动 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
02 |
行业ERP应用研究 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
03 |
搜集ERP供应商资料 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
04 |
公司现状调研 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
05 |
供应商初步筛选 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
06 |
² 建立内部项目组 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
07 |
确定项目范围 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
08 |
研究供应商产品 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
09 |
A系统研究 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
10 |
B系统研究 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
11 |
C系统研究 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
12 |
供应商确定 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
13 |
² 合同签订 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
14 |
内部流程重整 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
15 |
ERP基本资料建立 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
16 |
ERP实施前测试与培训 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
17 |
数据录入 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
18 |
新旧系统同步运行与调整 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
19 |
功能二次开发 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
20 |
² ERP系统试运行 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
21 |
系统交割,旧系统停用 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
22 |
系统上线并验收完成 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
23 |
² 项目结束 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
注:1~5已经完成
² 号,为项目整体内的里程碑进度,该项的实施决定项目的整体进程。
2,项目组近期任务
|
项目组任务 |
Apr.15 |
Apr.25 |
May.5 |
May.15 |
May.25 |
Jun.5 |
Jun.15 |
Jun.25 |
||||||||
01 |
了解项目使命及进度 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
02 |
研究详细内部需求 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
03 |
A系统研究 |
|
3天 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
04 |
系统研究总结 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
05 |
B系统研究 |
|
|
3天 |
|
|
|
|
|
|
|
|
|
|
|
|
|
06 |
系统研究总结 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
07 |
C系统研究 |
|
|
|
|
3天 |
|
|
|
|
|
|
|
|
|
|
|
08 |
系统研究总结 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
09 |
供应商综合评估 |
|
|
|
|
|
|
10天 |
|
|
|
|
|
|
|
|
|
10 |
供应商确认 |
|
|
|
|
|
|
|
|
10天 |
|
|
|
|
|
||
11 |
合同订立 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
12 |
项目实施 |
|
|
|
|
|
|
|
|
|
|
|
|
² 项目组成员每人4WD工作量,(但PMC需要5WD,MIS需要20WD的工作量)。
² 该进度会随着项目推行的实际需求调整。