IfcResourceTime
IfcResourceTime
实体定义
IfcResourceTime捕获有关构造资源的时间相关信息。
IFC4中的新实体。
Attribute definitions
# | Attribute | Type | Cardinality | Description | C |
---|---|---|---|---|---|
4 | ScheduleWork | IfcDuration | [0:1] | Indicates the total work (e.g. person-hours) allocated to the task on behalf of the resource. Note: this is not necessarily the same as the task duration (IfcTaskTime.ScheduleDuration); it may vary according to the resource usage ratio and other resources assigned to the task. | X |
5 | ScheduleUsage | IfcPositiveRatioMeasure | [0:1] | Indicates the amount of the resource used concurrently. For example, 100% means 1 worker, 300% means 3 workers, 50% means half of 1 worker's time for scenarios where multitasking is feasible. If not provided, then the usage ratio is considered to be 100%. | X |
6 | ScheduleStart | IfcDateTime | [0:1] | Indicates the time when the resource is scheduled to start working. | X |
7 | ScheduleFinish | IfcDateTime | [0:1] | Indicates the time when the resource is scheduled to finish working. | X |
8 | ScheduleContour | IfcLabel | [0:1] | Indicates how a resource should be leveled over time by adjusting the resource usage according to a specified curve. Standard values include: 'Flat', 'BackLoaded', 'FrontLoaded', 'DoublePeak', 'EarlyPeak', 'LatePeak', 'Bell', and 'Turtle'. Custom values may specify a custom name or formula. | X |
9 | LevelingDelay | IfcDuration | [0:1] | Indicates a delay in the ScheduleStart caused by leveling. | X |
10 | IsOverAllocated | IfcBoolean | [0:1] | Indicates that the resource is scheduled in excess of its capacity. | X |
11 | StatusTime | IfcDateTime | [0:1] | Indicates the date and time for which status values are applicable; particularly completion, actual, and remaining values. If values are time-phased (the referencing IfcConstructionResource has associated time series values for attributes), then the status values may be determined from such time-phased data as of the StatusTime. | X |
12 | ActualWork | IfcDuration | [0:1] | Indicates the actual work performed by the resource as of the StatusTime. | X |
13 | ActualUsage | IfcPositiveRatioMeasure | [0:1] | Indicates the actual amount of the resource used concurrently. | X |
14 | ActualStart | IfcDateTime | [0:1] | Indicates the time when the resource actually started working. | X |
15 | ActualFinish | IfcDateTime | [0:1] | Indicates the time when the resource actually finished working. | X |
16 | RemainingWork | IfcDuration | [0:1] | Indicates the work remaining to be completed by the resource. | X |
17 | RemainingUsage | IfcPositiveRatioMeasure | [0:1] | X | |
18 | Completion | IfcPositiveRatioMeasure | [0:1] | Indicates the percent completion of this resource. If the resource is assigned to a task, then indicates completion of the task on behalf of the resource; if the resource is partitioned into sub-allocations, then indicates overall completion of sub-allocations. | X |
Attribute inheritance
# | Attribute | Type | Cardinality | Description | C |
---|---|---|---|---|---|
IfcSchedulingTime | |||||
1 | Name | IfcLabel | [0:1] | Optional name for the time definition. | X |
2 | DataOrigin | IfcDataOriginEnum | [0:1] | Specifies the origin of the scheduling time entity. It currently differentiates between predicted, simulated, measured, and user defined values. | X |
3 | UserDefinedDataOrigin | IfcLabel | [0:1] | Value of the data origin if DataOrigin attribute is USERDEFINED. | X |
IfcResourceTime | |||||
4 | ScheduleWork | IfcDuration | [0:1] | Indicates the total work (e.g. person-hours) allocated to the task on behalf of the resource. Note: this is not necessarily the same as the task duration (IfcTaskTime.ScheduleDuration); it may vary according to the resource usage ratio and other resources assigned to the task. | X |
5 | ScheduleUsage | IfcPositiveRatioMeasure | [0:1] | Indicates the amount of the resource used concurrently. For example, 100% means 1 worker, 300% means 3 workers, 50% means half of 1 worker's time for scenarios where multitasking is feasible. If not provided, then the usage ratio is considered to be 100%. | X |
6 | ScheduleStart | IfcDateTime | [0:1] | Indicates the time when the resource is scheduled to start working. | X |
7 | ScheduleFinish | IfcDateTime | [0:1] | Indicates the time when the resource is scheduled to finish working. | X |
8 | ScheduleContour | IfcLabel | [0:1] | Indicates how a resource should be leveled over time by adjusting the resource usage according to a specified curve. Standard values include: 'Flat', 'BackLoaded', 'FrontLoaded', 'DoublePeak', 'EarlyPeak', 'LatePeak', 'Bell', and 'Turtle'. Custom values may specify a custom name or formula. | X |
9 | LevelingDelay | IfcDuration | [0:1] | Indicates a delay in the ScheduleStart caused by leveling. | X |
10 | IsOverAllocated | IfcBoolean | [0:1] | Indicates that the resource is scheduled in excess of its capacity. | X |
11 | StatusTime | IfcDateTime | [0:1] | Indicates the date and time for which status values are applicable; particularly completion, actual, and remaining values. If values are time-phased (the referencing IfcConstructionResource has associated time series values for attributes), then the status values may be determined from such time-phased data as of the StatusTime. | X |
12 | ActualWork | IfcDuration | [0:1] | Indicates the actual work performed by the resource as of the StatusTime. | X |
13 | ActualUsage | IfcPositiveRatioMeasure | [0:1] | Indicates the actual amount of the resource used concurrently. | X |
14 | ActualStart | IfcDateTime | [0:1] | Indicates the time when the resource actually started working. | X |
15 | ActualFinish | IfcDateTime | [0:1] | Indicates the time when the resource actually finished working. | X |
16 | RemainingWork | IfcDuration | [0:1] | Indicates the work remaining to be completed by the resource. | X |
17 | RemainingUsage | IfcPositiveRatioMeasure | [0:1] | X | |
18 | Completion | IfcPositiveRatioMeasure | [0:1] | Indicates the percent completion of this resource. If the resource is assigned to a task, then indicates completion of the task on behalf of the resource; if the resource is partitioned into sub-allocations, then indicates overall completion of sub-allocations. | X |
EXPRESS Specification
ENTITY IfcResourceTime
SUBTYPE OF (IfcSchedulingTime);
ScheduleWork : OPTIONAL IfcDuration;
ScheduleUsage : OPTIONAL IfcPositiveRatioMeasure;
ScheduleStart : OPTIONAL IfcDateTime;
ScheduleFinish : OPTIONAL IfcDateTime;
ScheduleContour : OPTIONAL IfcLabel;
LevelingDelay : OPTIONAL IfcDuration;
IsOverAllocated : OPTIONAL IfcBoolean;
StatusTime : OPTIONAL IfcDateTime;
ActualWork : OPTIONAL IfcDuration;
ActualUsage : OPTIONAL IfcPositiveRatioMeasure;
ActualStart : OPTIONAL IfcDateTime;
ActualFinish : OPTIONAL IfcDateTime;
RemainingWork : OPTIONAL IfcDuration;
RemainingUsage : OPTIONAL IfcPositiveRatioMeasure;
Completion : OPTIONAL IfcPositiveRatioMeasure;
END_ENTITY;
###########################
QQ 3087438119