SDLC (System Develop Life Cycle)
CC->ZBB->RTO->RTW->RDC->(RTM)
BVT
Build Verification Test. Automated test run by Test team to maintain baseline functionality for each build.
CC
Code Complete. All development work for the milestone completed, unit tested, code reviewed and BVT cases successfully run.
ZBB
Zero Bug Bounce. All bugs resolved within 48 hours
RC
Release Candidate. Build candidate for final release.
RTO
Release To Operations. Build has been released to the operations team for deployment.
RTW
Release To Web/World. Operations team has deployed the release into the production cluster.
RDC
Release Declared Complete. Operations team has signed-off on the stability of the release and rollback is no longer possible.
RTM
Release to Manufacturing.